Short answer: size a commercial solar plant from three limits — how much electricity you use during daylight, how much shadow-free roof area you have, and what the grid-connection rules allow for your connection — then confirm the design with a yield simulation for your site.
Step 1: understand the load
Collect 12 months of electricity bills and, if possible, interval data or a load profile. What matters most for rooftop solar is the daytime consumption: offices, schools, day-shift factories and hospitals use a large share of their power while the sun is up.
Step 2: measure the usable roof
Survey the roof for shadow from parapets, tanks, staircases and neighbouring buildings, and leave walkways for safe cleaning. Check the structure: RCC roofs and metal-sheet roofs need different mounting systems, and older sheets may need repair first.
Step 3: estimate generation
Use a solar simulation tool with Jaipur's weather data and your actual layout, tilt and orientation. Include realistic losses — soiling, temperature, wiring and inverter efficiency. Avoid rules of thumb when the investment is large.
Step 4: check grid and regulatory limits
The capacity you can connect may be linked to your sanctioned load or contract demand and to the DISCOM's current rules on net metering or other arrangements. Confirm these before finalising the size.
Step 5: match generation to use
A plant that produces far more than you can use during the day may export a lot to the grid; how that export is credited depends on the rules for your connection. Sizing close to your daytime use keeps more of the generation on site.
Special cases
- Hotels: combine with heat pumps scheduled to run during the day, which raises daytime use.
- Hospitals: solar supplies part of the daytime load; critical systems stay on existing backup.
- Schools: plan around holidays when daytime use falls.
Next step
See commercial solar EPC in Jaipur or request a commercial solar assessment.